Plan and authorise an isolation affecting more than 50 customers
You are the Field Supervisor and Permit Issuer for the Traralgon depot.
What has happened
Liam Fitzgerald has applied for permit PTW-26-0424 to replace a leaking valve on the 150 millimetre steel main on the Princes Highway service road at Morwell. The isolation will cut supply to 68 customers including a bakery, a childcare centre and a small hospital kitchen. The Permit to Work and Isolation Policy requires manager approval for any outage over 50 customers, a proven isolation plan, control centre notification and a relight plan for every customer. The application is missing the customer count justification, the second isolation point is not identified, and no traffic management plan is attached. Sam Whitlock wants the permit ready for issue on Monday 21 September.
Deliverables
- Gap review of the original permit application
- Corrected permit application
- Customer notification and relight plan
- Approval request and control centre note
- Job safety analysis
Documents to use
Systems to use
Permit to Work Register
Records every permit issued for work on live gas assets, from application through isolation and restoration to close out.
Field Work Orders
Tracks construction, maintenance and metering jobs from creation and scheduling through to completion, as laid drawings and close out.
Network Asset Register
The register of regulator stations, city gates, valves, cathodic protection units and other network facilities with their condition and last inspection.
Units of competency
Current on training.gov.au for the Gas Industry Training Package as at 10 September 2026.
UEGNSG011Conduct isolations under the permit to work system for gas industry worksitesUEGNSG214Coordinate and conduct gas distribution pipeline repair and modificationsUEGNSG037Supervise technical operations for gas distribution or transmissionUEGNSG052Establish a utilities infrastructure worksiteUEGNSG036Supervise and monitor contract workQualifications
UEG40222Certificate IV in Gas Supply Industry OperationsWhat to look for
Evidence guide
The student must identify the missing second isolation point, the manager approval trigger and the traffic management gap. The corrected application must show isolation proven by reading rather than valve position. The relight plan must prioritise vulnerable customers and state how each relight is recorded. The approval request must include a contingency. Assess supervision judgement, not just form completion.